84339 Unterdietfurt: Masonry work upper floor house 4 / start masonry work house 3

New building project 84339 Unterdietfurt near Eggenfelden (district Rottal-Inn):


In the last few weeks we were able to successfully complete the first floor of house 4 with intermediate partition walls. Furthermore, the exterior walls of the upper floor of house 4 as well as the first floor of house 3 with intermediate partition walls have already been bricked.


The masonry work of house 3 & house 4 (construction phase 1) will be completed in the course of November. Afterwards, the carpentry work (roof truss), tinsmith work and the installation of the building elements windows & doors will be continued directly.